Abu Dhabi National Energy Company (Taqa), Emirates Water and Electricity Company (Ewec), and a consortium comprising Saudi Arabia's Aljomaih Energy and Water Company and Singapore's Sembcorp Industries announced the AED 7.76 billion (approximately $2.1 billion) financial close for the Taweelah C power plant. Early construction works are underway on the 2.6-gigawatt gas-fired facility, which is scheduled to commence commercial operations in 2029.
China Energy Engineering Corporation holds the engineering, procurement, and construction (EPC) contract for the project. For the project company, Taqa will hold a 60% stake, with Aljomaih and Sembcorp holding the remaining 40%. The structure is reversed for the operations and maintenance entity, where the international partners will control 60% and Taqa 40%. Ewec previously executed a 21-year power purchase agreement in June to off-take the plant's electricity output.
The project is funded primarily through senior debt provided by six international and regional lenders, including the Industrial and Commercial Bank of China alongside HSBC, DBS, OCBC, KfW IPEX-Bank, and First Abu Dhabi Bank. Abu Dhabi Islamic Bank and Dubai Islamic Bank also participated in arranging the financing facility.
According to state news agency Wam, the plant is designed to supply flexible gas generation to support renewable integration and peak demand as Ewec projects its solar capacity to reach 15.5 GW by 2030 and exceed 35 GW by 2035, driven by a forecast 70% increase in electricity demand between 2026 and 2033.
Sources
- Enterprise · 2026-11-23