Abu Dhabi National Energy Company (TAQA), Emirates Water and Electricity Company (EWEC), Saudi Arabia's Aljomaih Energy and Water Company, and Singapore's Sembcorp Industries have announced the financial close of the AED 7.76 billion (approximately S$2.7 billion or US$2.11 billion) Taweelah C Independent Power Plant in Abu Dhabi.
The 2.6-gigawatt (GW) combined-cycle gas turbine (CCGT) plant is designed to provide flexible generation capacity and grid stability while supporting future integration of carbon capture technologies. The facility is scheduled to begin commercial operations in 2029 under a long-term power purchase agreement with EWEC that runs through 2050.
Under the project company structure, TAQA holds a 60% controlling stake, with the international consortium of Aljomaih Energy and Water Company and Sembcorp Industries holding the remaining 40%. The ownership split is reversed for the operations and maintenance entity, where the international consortium holds 60% and TAQA owns 40%.
Financing was secured primarily through senior debt provided and arranged by a consortium of international and regional banks, including the Industrial and Commercial Bank of China (ICBC), HSBC, DBS Bank, Oversea-Chinese Banking Corporation (OCBC), KfW International Project and Export Finance Bank, and First Abu Dhabi Bank, alongside Abu Dhabi Islamic Bank and Dubai Islamic Bank.
China Energy Engineering Corporation (Energy China) is executing the project under an engineering, procurement, and construction (EPC) contract. EWEC noted the project is part of a broader strategy to support rising power demand while expanding solar photovoltaic capacity towards 15.5 GW by 2030 and over 35 GW by 2035.
Sources
- 联合早报 · 2026-11-23