A disrupted project does not automatically relieve a business of its contractual obligations under UAE law, according to legal analysis published via Legal 500. Legal practitioners in Dubai highlight that commercial parties must differentiate between events causing complete impossibility and situations involving financial hardship, expensive delays, or liquidity shortages to avoid wrongful termination claims.
Under Federal Decree Law No. 25 of 2025, which introduced the current UAE Civil Transactions Law effective 1 June 2026, Article 236 governs situations of impossibility. For bilateral contracts, force majeure rendering performance impossible extinguishes reciprocal obligations and automatically ends the agreement. If the disruption is partial, a party may seek discharge of the affected obligation or court rescission, while temporary disruption in continuing contracts can support modification, partial discharge, or judicial rescission.
In contrast, Article 224 addresses unforeseen exceptional circumstances of a general nature that create extreme hardship and threaten severe loss while performance remains achievable. In such cases, courts have statutory discretion to balance parties' interests by reducing burdensome obligations to a reasonable level or ordering rescission; agreements seeking to exclude this judicial power are legally invalid. The guidance stresses that reduced commercial profitability alone does not satisfy the legal threshold for hardship.
The report notes that separate jurisdictions within the UAE maintain distinct legal frameworks. By comparison, DIFC Courts recorded 117 Civil and Commercial Division claims with a collective value of AED 2.6 billion in 2025 across its independent jurisdiction. For contracts under federal law, businesses are advised to gather the original contract, notices, amendment records, and verifiable evidence of disruption before pursuing formal relief or negotiations.